The High Court has restrained a creditor from presenting two winding-up petitions in a decision which illustrates the importance of genuine cross-claims in insolvency proceedings. In Amber Construction Services Limited v Ilyrian Construction Ltd [2026] EWHC 2603 (BP), the court prevented one petition from proceeding even though it accepted that the underlying debt was due and owing.

For company directors facing creditor enforcement, the decision provides useful reassurance. Receiving a statutory demand or being threatened with a winding-up petition, whilst threatening on many levels, does not automatically indicate wrongdoing by the directors. There are recognised legal options for challenging threatened insolvency proceedings, particularly where the company has a substantial claim of its own against the creditor.

The judgment, handed down on 16 October 2026, is particularly significant because the successful cross-claim arose under a different contract from the debt being pursued.


What happened in Amber Construction v Ilyrian Construction?

The proceedings arose from a dispute between two construction companies over payments relating to separate building projects at Alton Estate and Mander Court in London.

Ilyrian Construction Ltd had carried out subcontracting work for Amber Construction Services Limited. Following disagreements over payment, alleged defects and delays, Ilyrian served two statutory demands on 15 November 2025. It subsequently sought to rely on debts of £27,119.90 for the Alton project and £39,329 for the Mander Court project, excluding interest.

Amber disputed its liability and maintained that it had substantial claims against Ilyrian arising from alleged delays, inadequate resourcing and defective workmanship.

Rather than allowing the disputes to proceed towards winding-up petitions, Amber applied to the High Court under rule 7.24 of the Insolvency (England and Wales) Rules 2016 for injunctions restraining their presentation.

Chief Insolvency and Companies Court Judge Briggs granted final injunctions in respect of both statutory demands, although the reasons differed significantly between the two projects.


Why did the High Court restrain the Alton Estate winding-up petition?

The Alton Estate dispute concerned Ilyrian’s claim for £27,119.90 arising from construction works undertaken in 2019.

  • Amber argued that the payment application did not comply with the contractual requirements governing when payment became due. It also relied on a substantial cross-claim relating to alleged delays and defective work, together with a limitation defence.
  • The court accepted that the payment application failed to comply with the mandatory contractual provisions and therefore did not give rise to the payment obligation asserted by Ilyrian.
  • However, the court also examined the underlying cross-claim. Amber had produced contemporaneous documents, including a notice of default issued in November 2019 and subsequent payment notices from 2020, identifying alleged problems with Ilyrian’s performance.
  • Although there were weaknesses in the supporting financial evidence, the court considered the cross-claim sufficiently genuine and substantial to prevent winding-up proceedings.
  • The court also accepted that Amber had a substantial limitation defence. On the payment date supported by Ilyrian’s own evidence, the relevant contractual claim had become statute-barred by March 2026. Serving a statutory demand had not stopped the limitation period running.

These findings provided independent reasons why the Alton debt could not properly support the threatened winding-up petition.


Why was the Mander Court decision particularly important?

The Mander Court dispute produced the more significant finding for companies and creditors involved in commercial debt disputes.

Ilyrian claimed £39,329 for subcontracting work carried out in 2021. Amber sought to reduce that amount by relying on alleged defects, missing certification and associated rectification costs.

However, the High Court was not satisfied that Amber had established substantial grounds for disputing the Mander Court debt. The judge found that the supporting evidence for most of the proposed deductions was inadequate and concluded that the entire £39,329 was due and owing.

Ordinarily, an undisputed debt of this value could provide a basis for a creditor to consider winding-up proceedings, provided the other statutory requirements were satisfied.

The outcome was different because Amber had an existing cross-claim arising from the Alton Estate project.

The judge accepted that the net Alton cross-claim was £47,728.01, exceeding the Mander Court debt by £8,399.01. Importantly, the cross-claim was between the same parties acting in the same capacities, even though it arose under a separate construction contract. The court therefore restrained presentation of the Mander Court winding-up petition despite finding that the underlying debt was payable.

The central point is that an undisputed debt does not necessarily justify winding-up proceedings where the debtor has a genuine and substantial cross-claim which equals or exceeds that debt.


Can a cross-claim under a different contract prevent a winding-up petition?

Yes. The Amber Construction judgment confirms that a substantial cross-claim does not necessarily have to arise under the same contract as the debt relied upon by the creditor.

  • The court applied established principles from Re Bayoil SA [1999] 1 WLR 147. Those principles recognise that winding-up proceedings may be restrained where a debtor has a genuine and serious cross-claim equal to or exceeding the winding up petition debt, unless special circumstances justify a different outcome.
  • In the present case, Ilyrian argued that the Alton cross-claim should not affect its right to pursue the Mander Court debt because the claims arose from different projects.
  • The judge rejected that argument. The cross-claim was between the same parties in the same legal capacities, and the court found no special circumstances justifying presentation of the petition.

The decision does not mean that any allegation of financial loss will prevent winding-up proceedings. A cross-claim must have real substance and be supported by evidence capable of withstanding judicial scrutiny.

For companies involved in several commercial contracts with the same supplier, contractor or customer, the judgment is an important reminder that the wider relationship between the parties may need to be considered before insolvency proceedings are pursued.


What evidence is needed to establish a genuine cross-claim?

One of the most useful aspects of the judgment is the distinction the court drew between the evidence supporting the two disputes.

  • In relation to Alton Estate, Amber had retained correspondence and notices demonstrating that allegations of defective work and delay had been raised years before the statutory demands were served. Although the supporting calculations were not comprehensive, those earlier documents provided evidence that the cross-claim was genuine rather than a response manufactured to resist payment.
  • By contrast, the deductions proposed against the Mander Court debt were not adequately substantiated. The court was unwilling to accept several amounts claimed for rectification, certification and overheads where the supporting evidence did not establish a sufficient connection with the alleged defects.

This distinction matters because insolvency courts do not conduct a full trial of every commercial disagreement when considering whether to restrain a petition. They must nevertheless examine the evidence sufficiently to determine whether a dispute or cross-claim is genuine and substantial.

Contemporaneous contractual notices, correspondence, payment records, defect reports and supporting calculations can therefore be important in establishing whether winding-up proceedings are appropriate.


What does the judgment mean for creditors considering winding-up proceedings?

The decision also has consequences for creditors contemplating the use of winding-up proceedings to recover outstanding commercial debts.

A creditor may have a valid contractual entitlement to payment but still be unable to rely on insolvency proceedings where the debtor has a sufficiently substantial cross-claim.

The court’s decision does not extinguish the creditor’s underlying contractual rights. Nor does it mean that every commercial disagreement prevents a winding-up petition. The legal position depends on the strength of the dispute, the evidence available and whether any cross-claim equals or exceeds the relevant debt.

Creditors should therefore consider more than whether an invoice remains unpaid. They should examine correspondence about alleged defects, contractual deductions, threatened claims and other outstanding disputes between the parties.

Where substantial factual issues require determination, conventional civil proceedings or, where applicable, construction adjudication may provide a more appropriate route to resolving the underlying dispute.

FWJ’s winding-up petition guidance explains the wider procedures available to creditors and companies facing insolvency action.


What should company directors take from the October 2026 ruling?

For directors who have received a statutory demand or are facing the threat of a winding-up petition, the judgment demonstrates the importance of reviewing the complete contractual and financial relationship with the creditor.

  • A company may have an arguable defence based on the debt itself, but it may also have a separate claim capable of affecting whether insolvency proceedings are appropriate. Identifying and evidencing those claims can materially influence the available options.
  • Where there are grounds to challenge threatened proceedings, the company may be able to seek an injunction before a petition is presented. If a petition has already been issued, different procedural steps may be necessary to prevent advertisement or challenge the petition.

These distinctions matter because the consequences of a winding-up petition can extend beyond the immediate debt dispute. Once a petition has been presented, it may affect the company’s banking arrangements and ability to make payments. If a winding-up order is subsequently made, transactions following presentation may be affected by section 127 of the Insolvency Act 1986.

Directors should also consider their wider duties if the company is insolvent or approaching insolvency. The existence of a petition does not automatically make directors personally liable for company debts, but subsequent decisions about trading, creditor payments and company assets may be examined if liquidation follows.

FWJ’s guidance on defending a winding-up petition explains the available procedural options. Where proceedings have already affected company banking arrangements, our validation order guide addresses the circumstances in which court approval of payments may be required.


What does Amber Construction v Ilyrian establish for future disputes?

The decision illustrates the distinction between establishing that a debt is payable and establishing that it can properly support a winding-up petition.

The High Court found that Ilyrian was entitled to payment of the Mander Court debt, yet restrained insolvency proceedings because Amber had a genuine and substantial cross-claim arising from a different contract. It also demonstrated that the court will distinguish between evidenced cross-claims and unsupported objections, rather than accepting every disputed figure at face value.

The judgment does not introduce an entirely new legal test. Instead, it applies established principles governing disputed debts and cross-claims to a commercial relationship involving separate contracts.

For creditors and company directors, the practical significance is clear: the existence of an unpaid debt is only part of the analysis when deciding whether winding-up proceedings can properly be pursued.


How Francis Wilks & Jones can help

Francis Wilks & Jones advises companies, directors and creditors across England and Wales on winding-up petitions, disputed debts and commercial insolvency proceedings.

Where a company faces a statutory demand or threatened petition, we can review the underlying liability, assess the strength of any cross-claim, consider the available evidence and advise on appropriate steps to protect the company’s position.

We also advise creditors on the suitability of winding-up proceedings and alternative methods of recovering disputed commercial debts.

If your company is involved in a similar dispute, contact Francis Wilks & Jones to discuss the circumstances and the options available.

Legal source: Amber Construction Services Limited v Ilyrian Construction Ltd [2026] EWHC 2603 (BP), High Court, 16 October 2026. Read the full judgment at The National Archives.

Key contacts

Andrew Carter

Andrew Carter

Partner

Hardeep Singh

Hardeep Singh

Trainee Solicitor

Gemma Newing

Gemma Newing

Senior Associate

View full team

Case studies

View all case studies

Contact us in confidence